The Environment Agency is set to begin essential works to replace the Canklow Regulator on the River Rother, which runs into the River Don in Rotherham town centre
This work is expected to take approximately five to six months to complete. Once operational, the new flood gate will play a crucial role in managing water flows and reducing the long-term risk of flooding for homes and businesses downstream.
The works form part of a wider project to enhance flood resilience for communities along the River Don between Rotherham and Doncaster.
Starting in April 2025, the existing flood gate at Canklow will be removed and replaced with a new, more resilient structure.
The Environment Agency has warned there could be a “small temporary increase in flood risk to downstream communities” during the works.
Replacing the gate at Canklow over the coming months, aims to ensure that there will be two regulators in operation ahead of next winter.
Kimberley MacPherson, Environment Agency Operations Manager said: We know the devastating impact that flooding can have so the decision to proceed with these works has been carefully considered.”
“We will be taking as many precautions as possible to mitigate any temporary increase in flood risk.”
The Environment Agency also operates the Meadowgate and Woodhouse Mill regulators.
The regulators are used to hold back and store water in flood storage areas on the River Rother during flood events. This โslows the flowโ and reduces the risk of flooding to properties downstream on the River Don between Rotherham and Doncaster.